Dell 1000W User's Guide Page 73

  • Download
  • Add to my manuals
  • Print
  • Page
    / 135
  • Table of contents
  • BOOKMARKS
  • Rated. / 5. Based on customer reviews
Page view 72
73
Configuring the Software
|
Testing the UPS
You can perform a UPS self‐test immediately or schedule a UPS self‐test.
Performing a UPS Self‐Test Immediately
Select Request Battery Test from the UPS menu to open the Request Battery Test window
(see Figure 73).
NOTE:
If the UPS Control Commands from Serial Port setting is disabled, configuration and load control
commands are restricted to the LCD only. This setting must be enabled from the LCD before you can select
Request Battery Test.
Figure 73. UPS Self‐Test Immediately Window
Select the Self‐Test option and click OK to start the UPS self‐test.
Click Cancel Current UPS Self‐Test from the UPS menu to cancel the self‐test process immediately.
Page view 72
1 2 ... 68 69 70 71 72 73 74 75 76 77 78 ... 134 135

Comments to this Manuals

No comments